H.R. 7066: SHIELD Act
Sponsor
Mike Levin
Democrat · CA-49
Bill Progress
Latest Action · Jan 14, 2026
Referred to the House Committee on Energy and Commerce.
Why it matters
Power demand from very large users is rising fast, and this bill would require utilities and states to decide within 1 year of enactment how to stop households and smaller businesses from paying for grid upgrades tied to facilities with peak demand above 75 megawatts.
The SHIELD Act — short for the “Stopping Hikes In Electricity from Large Load Demands Act” — would add new standards to the Public Utility Regulatory Policies Act of 1978. Its core rule is that a “large load facility” must be treated as its own class of electric consumers, and electric utilities must fully recover all costs of grid upgrades from that class. The bill is very specific about scope: it covers generation, transmission, and distribution upgrades, including local facilities, and it even says the large-load class must cover costs if a facility later shuts down or uses less electricity than projected when the upgrade was built.
The bill defines a large load facility as a facility, or aggregation of facilities at a single site, with peak demand exceeding 75 megawatts. It also draws a line around what does not count: existing facilities are exempt if their increased demand is predominantly caused by electrification or by measures to reduce greenhouse gas emissions. That means the bill is aimed more at entirely new or newly intensified very large loads than at existing sites switching equipment to cleaner technologies.
The measure also tries to shape how utilities handle service requests from these large customers. Utilities would have to prioritize requests from large load facilities that agree to use demand reduction features such as energy efficiency or conservation measures, onsite energy storage, or demand response and load flexibility technologies. They would also have to prioritize facilities that meet 100% of their demand with zero-emission electric energy generated onsite or bought through a power purchase agreement within the same balancing authority. The bill defines zero-emission electric energy broadly as electricity generated without greenhouse gas emissions, including solar, wind, geothermal, hydroelectric, tidal, fission, or fusion.
The timetable is quick. State regulatory authorities and nonregulated utilities must start considering these new standards, or set a hearing date, no later than 1 year after enactment, and they must finish and make a determination no later than 2 years after enactment. Then, within 30 days after making that determination, they must send a report to the House Committee on Energy and Commerce and the Senate Committee on Energy and Natural Resources explaining both the process they used and why they decided as they did. There is an off-ramp for states that already acted before enactment: the requirement does not apply if a state already implemented a comparable standard, already held a proceeding on one, or if the state legislature voted on implementation within the 3-year period ending on the date of enactment.
What does H.R. 7066 do?
Large loads above 75 megawatts pay their own way
The bill defines a “large load facility” as a facility or aggregation of facilities at a single site with peak demand exceeding 75 megawatts, and requires utilities to treat that group as a separate class of electric consumers for ratemaking and cost recovery.
Full recovery of grid upgrade costs
Electric utilities must fully recover all costs tied to serving the large load facility class, including generation, transmission, distribution, and local facility upgrades. The rule also applies if the facility later ceases operations or uses less energy than was projected when the upgrade was planned.
Priority service for 100% zero-emission power
Utilities must prioritize service requests from large load facilities that agree to meet 100% of their demand with zero-emission electric energy generated onsite or procured through a power purchase agreement within the same balancing authority.
Demand-cutting features move projects up
Large load facilities get priority if they agree to use demand reduction features such as energy efficiency or conservation measures, onsite energy storage, or demand response and load flexibility technologies, which is designed to reduce strain from loads above the 75-megawatt threshold.
States must act within 1 year and finish in 2
State regulatory authorities and nonregulated utilities must begin considering the new standards, or set a hearing date, not later than 1 year after enactment, and must complete consideration and make a determination not later than 2 years after enactment.
30-day reporting rule with 3-year exemption lookback
Within 30 days after a determination, states or nonregulated utilities must report to the House Committee on Energy and Commerce and the Senate Committee on Energy and Natural Resources. They are exempt if, before enactment, they already implemented or considered a comparable standard, or if the state legislature voted on one within the 3-year period ending on enactment.
Who benefits from H.R. 7066?
Residential electricity customers
They stand to benefit if costs for major grid upgrades are no longer spread across general ratepayers and are instead fully recovered from the class of facilities with peak demand exceeding 75 megawatts.
Small and mid-size businesses
Businesses that are not part of the new large-load class could avoid paying for generation, transmission, distribution, and local facility upgrades built mainly for very large new customers.
Utilities managing grid reliability
Utilities get a clearer framework to require full cost recovery from very large loads and to prioritize projects that include onsite storage, demand response, or 100% zero-emission energy within the same balancing authority.
Large facilities investing in cleaner, flexible power
Facilities above 75 megawatts that agree to use demand reduction features or meet 100% of demand with zero-emission electricity could receive priority in utility service requests over other large-load applicants.
Who is affected by H.R. 7066?
Data centers, factories, and other very large new power users
If they exceed 75 megawatts of peak demand at a single site, they would likely face direct responsibility for grid upgrade costs, including cases where future usage falls short of original projections or the facility later shuts down.
State regulatory authorities
They must commence consideration or set a hearing date within 1 year after enactment, complete a determination within 2 years, and submit a report within 30 days to two congressional committees unless a pre-enactment exemption applies.
Nonregulated utilities
Utilities outside traditional state commission structures still have to consider and determine whether to adopt the new standards on the same 1-year, 2-year, and 30-day timeline.
Existing facilities increasing use due to electrification
They are affected differently because the bill says an existing facility is not a “large load facility” when its higher demand is predominantly caused by electrification or by measures to reduce greenhouse gas emissions.
H.R. 7066 Common Questions
How much power use makes a facility a large load facility under the SHIELD Act?
A facility, or multiple facilities at one site, qualifies if peak demand exceeds 75 megawatts under the SHIELD Act (Sec. 2(b)).
Can utilities charge data centers or other 75 MW+ customers for all grid upgrade costs under the SHIELD Act?
Yes. Under the SHIELD Act, utilities must fully recover generation, transmission, distribution, and local upgrade costs from the large load facility class (Sec. 2(a)).
Does the SHIELD Act make large power users pay even if the project shuts down or uses less electricity than expected?
Yes. According to H.R. 7066 Sec. 2(a), the large load facility class still covers upgrade costs if a facility ceases operations or uses less energy than projected.
What are the deadlines for states to act under the SHIELD Act?
States and nonregulated utilities must begin considering the standards or set a hearing date within 1 year, and finish with a determination within 2 years under the SHIELD Act (Sec. 2(c)).
Does the SHIELD Act require states to send a report to Congress within 30 days?
Yes. Under the SHIELD Act (Sec. 2(c)), a report must be sent within 30 days after the determination to the House Energy and Commerce Committee and Senate Energy and Natural Resources Committee.
Can a large load facility get priority service if it uses 100% zero-emission electricity?
Yes. Under the SHIELD Act (Sec. 2(a)), utilities must prioritize service requests from large load facilities that agree to meet 100% of demand with qualifying zero-emission electricity.
Which energy sources count as zero-emission electric energy under the SHIELD Act?
The SHIELD Act defines zero-emission electric energy to include solar, wind, geothermal, hydroelectric, tidal, fission, and fusion (Sec. 2(b)).
Does onsite battery storage or demand response help a large load project get utility priority under the SHIELD Act?
Yes. Under the SHIELD Act (Sec. 2(a)), utilities must prioritize large load facilities that agree to use energy efficiency, conservation, onsite storage, or demand response and load flexibility tools.
Is an existing factory exempt from the SHIELD Act if its higher power demand comes from electrification?
Yes. According to H.R. 7066 Sec. 2(b), existing facilities are excluded if the increased demand is predominantly caused by electrification or measures to reduce greenhouse gas emissions.
Can a state skip the SHIELD Act review if it already passed or considered a similar rule recently?
Yes. Under the SHIELD Act (Sec. 2(c)), the requirement does not apply if the state already implemented or considered a comparable standard, or its legislature voted on one within the prior 3 years.
Based on H.R. 7066 bill text
HR7066 Legislative Journey
House: Committee Action
Jan 14, 2026
Referred to the House Committee on Energy and Commerce.
About the Sponsor
Mike Levin
Democrat, California's 49th congressional district · 7 years in Congress
Committees: Appropriations
View full profile →
Cosponsors (13)
All 13 cosponsors are Democrats. Cosponsors represent 8 states: California, Florida, Illinois, and 5 more.
Kathy Castor
Democrat · FL
Mike Quigley
Democrat · IL
Greg Landsman
Democrat · OH
Daniel Goldman
Democrat · NY
George Latimer
Democrat · NY
Sean Casten
Democrat · IL
Chellie Pingree
Democrat · ME
Seth Magaziner
Democrat · RI
Ted Lieu
Democrat · CA
Kevin Mullin
Democrat · CA
Salud Carbajal
Democrat · CA
Emilia Sykes
Democrat · OH
Committee Sponsors
Energy and Commerce Committee
3 of 54 committee members cosponsored
21 Democrats across this committee haven't cosponsored yet. Mobilize their constituents
What laws does H.R. 7066 change?
3 changes
Sections Amended
Section 111(d) of Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(d))
adding at the end the following: ``(22) Large load facility class
Section 111 of Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621)
adding at the end the following: ``(e) Definitions
Section 124 of Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2634)
inserting ``In the case of each standard established by paragraphs (22) and (23) of section 111(d), the reference contained in this section to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of such paragraphs (22) and (23)
H.R. 7066 Quick Facts
- Committee
- Energy and Commerce
- Chamber
- House
- Policy
- Energy
- Introduced
- Jan 14, 2026
Referred to the House Committee on Energy and Commerce.
Jan 14, 2026
Official Sources
Official Congress.gov page for the SHIELD Act with bill text, status, and actions.
DOE's grid modernization work provides official federal context for transmission, distribution, and reliability upgrades discussed in the bill.
The Office of Electricity is the main federal office focused on grid reliability, transmission, and electric system resilience relevant to the bill's utility standards.
This EPA resource provides official information on procuring zero-emission electricity, including mechanisms like power purchase agreements relevant to the bill.
H.R. 7066 Bill Text
“To amend the Public Utility Regulatory Policies Act of 1978 to add a standard relating to the consideration of large load facilities as a class of electric consumers, and for other purposes.”
Source: U.S. Government Publishing Office
Get notified when H.R. 7066 moves
Committee votes, floor action, cosponsor changes — straight to your inbox.
Bill alerts + Legisletter's monthly briefing. Unsubscribe anytime.
Energy Bills
9 related bills we're tracking
Energy Choice Act
Placed on the Union Calendar, Calendar No. 412.
Feb 4, 2026
Heating and Cooling Relief Act
Referred to the Committee on Energy and Commerce, and in addition to the Committee on Education and Workforce, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.
Mar 31, 2025
Electricity Transmission Scorecard Act
Referred to the House Committee on Energy and Commerce.
Nov 20, 2025
Critical Mineral Consistency Act of 2025
Received in the Senate. Read twice. Placed on Senate Legislative Calendar under General Orders. Calendar No. 348.
Mar 4, 2026
Homeowner Energy Freedom Act
Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.
Feb 25, 2026
CORE Act of 2025
Ordered to be Reported in the Nature of a Substitute by the Yeas and Nays: 25 - 18.
Jun 25, 2025
Home Appliance Protection and Affordability Act
Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.
Feb 25, 2026
Net Metering Protection Act
Referred to the House Committee on Energy and Commerce.
Sep 18, 2025
GRID Act
Referred to the House Committee on Energy and Commerce.
Oct 31, 2025
Trending Right Now
Bills gaining momentum across Congress
Congressional Tribute to Constance Baker Motley Act of 2025
Referred to the House Committee on Financial Services.
Sep 11, 2025
To designate the facility of the United States Postal Service located at 890 East 152nd Street in Cleveland, Ohio, as the "Technical Sergeant Alma Gladys Minter Post Office Building".
Received in the Senate and Read twice and referred to the Committee on Homeland Security and Governmental Affairs.
Apr 15, 2026
Love Lives On Act of 2025
Subcommittee Hearings Held
Feb 3, 2026
Tracking Energy in Congress? Monitor bills, track cosponsor momentum, and launch advocacy campaigns — all from one advocacy platform.